-4.2 C
Ottawa
Thursday, April 10, 2025

Hydro-Québec scores legal victory in Maine over $1B US transmission line project

Date:

Montreal

Thank you for reading this post, don't forget to subscribe!

Hydro-Québec scored an important legal victory in a courtroom south of the border to allow its $1-billion US transmission line project in Maine to go forward, which paves the way for the province’s utility to sell hydroelectricity to the state of Massachusetts.

Project is necessary to allow sale of hydroelectricity to state of Massachusetts

CBC News

·

There is a large building.

Maine Superior Court has ruled in favour of Hydro-Québec and its U.S. partners in a court case regarding the utility’s project to build a transmission line. (Paul Chiasson/Canadian Press)

Hydro-Québec has scored an important legal victory in a courtroom south of the border to allow its $1-billion US transmission-line project in Maine to go ahead.

The transmission line, which would span 336 kilometres between Quebec and Maine, is a pivotal part of the provincial utility’s plan to sell hydroelectricity to the commonwealth of Massachusetts.

On Thursday, Maine Superior Court ruled in favour of Hydro-Québec and its U.S. partners. According to local media reports, the court found that the project already had the necessary permits prior to being rejected by 59 per cent of voters in a referendum in November 2021. Work was suspended a few weeks later.

Last August, the Maine Supreme Court ruled that referendum was unconstitutional. It also sent the case back to the Superior Court level in order to have a ruling on the issue of permits.

Hydro-Québec’s partner in Maine, NECEC, has already spent nearly $450 million US on the project, which is about 43 per cent of the total projected cost, according to documents presented in court.

If the project were abandoned, Hydro-Québec estimates that it would lose nearly $530 million on top of potentially losing $10 billion in revenue over 20 years.

The utility also claimed it had spent an additional $160 million as of the end of last year in connection with agreements it has struck in connection with the project.

The utility has said that the deal with the state of Massachusetts would reduce greenhouse gases by three million tonnes, the equivalent of taking 700,000 cars off the road.

“We are satisfied with the ruling. This was our biggest legal obstacle to the project,” said Lynn St-Laurent, a spokesperson for Hydro-Québec.

Hydro-Québec had initially hoped for the transmission line to be up and running by December 2022, but the legal wrangling caused significant delays.

St-Laurent said it’s too early to know when work can resume and when the project will be completed, especially since there is a possibility that Thursday’s ruling will be appealed.

With files from La Presse Canadienne

know more

Popular

More like this
Related

Amazon delays first Kuiper internet satellite launch due to bad weather

United Launch Alliance Atlas V rocket carrying the first...

OpenAI says Musk has run ‘unlawful campaign of harassment’ against company in lawsuit

Sam Altman, left, and Elon Musk.Muhammed Selim Korkutata |...

Jim Cramer shares 4 lessons learned from Trump tariff turmoil

After President Donald Trump issued a 90-day pause on...

Slot ‘failed’ and ‘third-rate’ Van Dijk slammed as Liverpool ‘wailing’ continues

Some Liverpool fans have allowed the dust to settle and accepted Everton earned their draw and celebration. Some can’t quite let Michael Oliver go just yet. Send your thoughts to theeditor@football365.com. Walk on It’s been… not interesting per se, but… let’s say diverting to see (many, not all to be fair) Liverpool fans wailing about the derby . The